Long Lake Improvement Projects - Minnehaha Creek Watershed District (MCWD)

Overview

In the 1990s, Minnehaha Creek Watershed District (MCWD) oversaw the construction of wet detention basins, an alum treatment, and the enhancement of existing sedimentation basins to reduce the annual load of nutrients and sediments delivered to Long Lake. Two ponds were built to reduce the annual loading of nutrients and sediment delivered to Long Lake via runoff from the northern watershed. The alum treatment removed phosphorous from the water and improved the lake’s clarity by sealing the sediments. MCWD enhanced existing sedimentation basins in the city of Long Lake and Nelson Lakeside Park to reduce the load of nutrients and sediment to Long Lake from two major storm sewered subwatersheds. To complement this work, MCWD also restored shoreland vegetation on a section of Long Lake’s west shoreline in Nelson Lakeside Park. 

In 1989, MCWD with assistance from the Minnesota Pollution Control Agency (MPCA), through a Clean Water Partnership (CWP) grant, conducted a diagnostic study of Long Lake that characterized and quantified the causes contributing to the decline in water quality in the lake, developed numerical water quality goals, and determined performance standards for a plan to improve water quality and achieve the desired goals. This study, done with the support of local municipalities, laid the foundation for the projects undertaken in the Long Lake area in the 1990s.

At a Glance

  • Long Lake
  • Long Lake Creek Subwatershed
  • Status: Complete
  • 1999

MCWD Staff Contact

Tiffany Schaufler, MCWD

tschaufler@minnehahacreek.org

952-641-4513

Supporting Materials

Long Lake Creek Roadmap

Project Cost

$2,200,000

Project Updates

Summer 2023

MCWD recently developed a draft roadmap to document additional project opportunities in the Long Lake Creek subwatershed. The Long Lake Creek Roadmap includes MCWD-led projects as well as potential projects for partners to pursue with District support.

Project Timeline

conversation icon

Planning Phase

Expand details

Planning Phase

1989 — Diagnostic study of Long Lake water quality conduced

October 1991 — Draft feasibility study produced

October 1993 — Planning phase completed

research paper icon

Design Phase

Expand details

Design Phase

December 1993 — Design phase begins

May 1995 — Final design report completed

construction icon

Construction Phase

Expand details

Construction Phase

June 1996 — Alum treatment conducted on Long Lake

Fall 1995 — Construction of wet detention and sedimentation basins started

Winter 1996 — Construction of wet detention and sedimentation basins completed

Winter 1998 — Wetland constructed

1999 Shoreline restoration completed 

balanced landscape icon

Project completion

Expand details

Project Completion

1999 — Project completed

By the Numbers

181

acres

treated with Alum

50

percent

of phosphorus removed by two detention basins

20

percent

of phosphorus removed by City park detention basin

2.4

acres

of upland and wetland habitat provided


Project Highlights

  • Two wetland detention ponds 
  • Alum treatment 
  • Sedimentation basins 
  • Shoreline restoration 

Partnership

MCWD partnered with local municipalities, including the Cities of Medina, Orono, and Long Lake to conduct the studies associated with this project.  

MN MPCA logo

Funding

Project Cost: $2,200,000

The MPCA’s Clean Water Partnership grant supplied funding for the diagnostic study.  MCWD provided funding through its levy for the remaining project costs.